McMillan Shakespeare Group “offers a suite of products and services across workplace benefits, consumer finance and asset management.”
Internal Staff Relocation
We moved 254 staff internally for McMillan Shakespeare Group. The churn work was completed in three moves at Melbourne Central Tower, 360 Elizabeth Street. “At approximately 65,000sqm and 51 floors, Melbourne Central Tower is one of Melbourne’s most prominent commercial buildings and has forever changed the city’s skyline with its striking design”.
Move 1 – 66 Staff Internal Relocation
- 17 personal computers (disconnect reconnect)
- 49 phones
- 66 clerical chairs
- 66 mobile pedestals
Move 2 – 88 Staff Internal Relocation
- 88 personal computers (disconnect reconnect)
- 88 phones
- 88 clerical chairs
- 88 mobile pedestals
- 200 Egans crates
Move 3 – 100 Staff Internal Relocation
- 100 personal computers (disconnect reconnect)
- 100 phones
- 100 clerical chairs
- 100 mobile pedestals
- 120 Egans crates